A construction loan does not fund all at once. The lender releases money in installments, called draws, as work is completed. Each draw follows the same cycle.
- The contractor submits a pay application for work completed that month, with backup for materials stored on or off site.
- The sponsor's team reviews it against the schedule of values (the contract price broken into line items) and the work in place.
- The draw request goes to the lender with the pay application, invoices for soft costs, updated budget, and lien waivers from the contractor and major subcontractors for the prior payment.
- The lender's construction monitor inspects the site and confirms the percentage complete.
- The title company updates the title to confirm no new liens have been filed.
- The lender funds, often holding back retainage, a percentage of each payment kept until the work is complete.
On private projects in Texas, the owner must also reserve 10 percent of the contract price until 30 days after the work is completed, and lien waivers must substantially follow the statutory forms.
(Source: Tex. Prop. Code Secs. 53.101 and 53.284.)
Where draws stall
- Pay applications that claim more progress than the construction monitor sees
- Missing lien waivers
- Change orders not yet approved by the lender
- A budget line that has run out, with no approved reallocation of contingency
How to keep draws moving
- Agree the draw calendar, forms and backup with the lender before the first draw.
- Keep the budget, schedule of values and change order log reconciled every month.
- Collect lien waivers as payments are made, not at the end.
Where TJDM is the owner's representative, we prepare the draw request for the sponsor, and the lender's construction monitor checks it.
General information only. Not legal, tax, accounting, investment or engineering advice.