Most construction loan delays start with two documents that disagree, such as a budget that does not match the contractor's bid.

Construction lenders underwrite three things: the sponsor, the project and the plan to repay. A package that answers all three on the first read is easier to underwrite.

Sponsor

Organization chart, guarantor financial statements, a schedule of real estate owned (every property the sponsor holds, with its debt) and a summary of comparable projects completed. Lenders typically test guarantor net worth and cash on hand against the loan amount.

Project

Site control, survey and title commitment, zoning and entitlement status, environmental reports, and the design team and contractor with their qualifications.

Budget

Hard and soft costs, contingency, interest reserve (money set aside to pay loan interest during construction) and developer fee, with the basis for each number. Lenders compare the budget to the contractor's bid and to the appraisal, and expect a fixed-price contract or a maximum-price contract, or a clear plan for the cost risk if there is none.

Schedule

Design, permitting, construction and lease-up, with the dates that matter to the loan, such as completion and stabilization.

Capital plan

Sources and uses, the equity already spent and how any subordinate capital or incentives fit. Lenders typically require equity to be fully funded, and documented, before the first loan draw. On floating-rate loans they often require an interest rate cap.

Guarantees, bonds and insurance

Completion and carry guarantees, with financial statements that support them; payment and performance bonds or a lender-accepted alternative; builder's risk and liability insurance naming the lender; and consents from the architect and contractor to assign their contracts to the lender if the borrower defaults.

Exit

The long-term loan or sale assumptions and the market evidence behind rents, occupancy and pricing.

Third-party reports

Appraisal, plan and cost review, environmental, and where needed geotechnical and market studies. Lenders order some of these themselves.

Where packages break

Most packages break in one of three places: a budget that does not match the bid, a schedule that does not match permit status, or equity that has not been documented. Reconciling those before submission saves weeks of questions.

General information only. Not legal, tax, accounting, investment or engineering advice.

Headquarters

Based in Dallas-Fort Worth

Our office is in Arlington, Texas. We work in Texas and across the United States, and take on international projects case by case.

About the firm


Tell us about your project

Send the asset type, location, size, stage and timing. We will reply to set up a first call.

Institutional lenders: see how we work with you.