Data centers and digital infrastructure
A data center opens when the power arrives. Since Senate Bill 6, Texas asks large loads in the ERCOT region for site control, study fees and financial commitments before most projects have a tenant.
Market
What is driving projects
Figures as of November 2026.
ERCOT, which runs most of the Texas power grid, reported in July 2026 that it was tracking about 474 gigawatts of large loads seeking interconnection, about 90 percent of them data centers.
(Source: ERCOT, presentation to the Senate Committee on Business and Commerce, July 29, 2026.)
Senate Bill 6 (2025) directs the Public Utility Commission to set interconnection standards for large loads in the ERCOT region, at a 75-megawatt threshold unless the Commission sets a lower one, including a study fee of at least $100,000, proof of site control and financial commitments for transmission.
(Source: Tex. Util. Code Sec. 37.0561, added by SB 6, 89th Legislature.)
The Public Utility Commission adopted rules implementing those standards in September 2026 (16 TAC Sec. 25.194).
(Source: PUCT Project No. 58481.)
On September 21, 2026, the Governor asked TCEQ to suspend permits sought by data centers pending power grid and water audits by ERCOT and the Texas Water Development Board.
(Source: Office of the Governor, letter to TCEQ, September 21, 2026.)
Capital
Typical capital sources
- Sponsor equity and joint venture partners
- Development equity for land and power work, which now comes earlier under SB 6
- Construction debt sized to a creditworthy tenant lease, refinanced with term loans or bonds backed by the lease
- Infrastructure funds that finance sites with power secured and the building shell, before the tenant fits out the interior
- Where a project raises outside equity, the sponsor's securities counsel and, where required, a registered broker-dealer handle it.
Capital
Capital by phase
Illustrative. Not a TJDM transaction.
- 1
Land and power: sponsor and development equity
- 2
Shell and core: construction debt against a signed lease
- 3
Tenant fit-out: tenant capital or equipment financing
- 4
Stabilized: term loan or securitized debt
Underwriting
What lenders underwrite
- The tenant's credit and the lease term against the loan term
- Whether the power path, including curtailment terms (when the utility or ERCOT can cut the site's power), supports the lease
- Permits, including any state permit holds that apply to data centers
Underwriting
What we plan for
- Utility and ERCOT study timelines and their costs
- Water for cooling, and its permitting
- Backup generation permitting
- Lead times for transformers and switchgear
How TJDM helps
How TJDM helps
- 01
Infrastructure
Water and wastewater, data centers and digital infrastructure, and energy generation and storage.
Explore - 02
Project finance
Senior and mezzanine debt, preferred equity structuring and public incentives, with TJDM capital in select projects.
Explore - 03
Global sourcing
Supplier selection, third-party inspection, logistics and supply chain planning for project materials.
Explore - 04
Construction delivery
Program management from planning to handover, coordinating contractors on scope, schedule and budget.
Explore
Headquarters
Based in Dallas-Fort Worth
Our office is in Arlington, Texas. We work in Texas and across the United States, and take on international projects case by case.
Tell us about your project
Send the asset type, location, size, stage and timing. We will reply to set up a first call.
Institutional lenders: see how we work with you.