Power first: what SB 6 means for data center schedules

Texas now asks large power users to commit earlier, prove more and accept interruption. Each change moves cost and risk earlier in the project.

In June 2025, Texas enacted Senate Bill 6, a new framework for large electrical loads in the ERCOT region. It added Section 37.0561 to the Utilities Code, which applies to new or expanded loads of 75 megawatts or more at a single site unless the Commission sets a lower one. Requirements include a study fee of at least $100,000, proof of site control and disclosure of duplicate requests filed elsewhere. The Public Utility Commission adopted implementing rules in September 2026 in Project No. 58481 (16 TAC Sec. 25.194), with a flat $100,000 study fee.

(Sources: SB 6, 89th Legislature, enrolled; PUCT Project No. 58481.)

The scale explains the change: in July 2026, data centers made up about nine in ten of the large-load requests in ERCOT's queue (see Data centers). Then, on September 21, 2026, the Governor asked TCEQ to suspend permits sought by data centers pending grid and water audits.

(Sources: ERCOT, presentation to the Senate Committee on Business and Commerce, July 29, 2026; Office of the Governor, letter to TCEQ, September 21, 2026.)

SB 6 also changes reliability terms. Loads connected at transmission voltage after December 31, 2025 must have a protocol, and the equipment installed before connection, that allows them to be curtailed during firm load shed (the rotating outages ERCOT orders in a grid emergency). ERCOT must also run a competitively procured demand reduction service for large loads of 75 megawatts or more. And the standards require large loads to make financial commitments toward the transmission built to serve them.

(Sources: Tex. Util. Code Secs. 37.0561(h) and 39.170, added by SB 6.)

For sponsors, power work now starts earlier and costs real money.

That changes the capital plan. Early equity has to cover interconnection costs that used to come later. Lenders and tenants ask for the utility's study results and signed agreements. And the delivery schedule runs from a date the utility has confirmed for switching on the power, with transformers and switchgear ordered to match.

What a lender will ask

  • The interconnection study stage, and any agreement signed
  • Financial security posted to the utility, and who funded it
  • The curtailment terms, and whether the tenant lease accepts them
  • Permits for backup generation
  • Order dates for long-lead electrical equipment

The Commission's rule and ERCOT's implementing procedures continue to develop. Confirm current requirements with utility counsel before committing study fees.

Figures as of November 2026.

General information only. Not legal, tax, accounting, investment or engineering advice.

Headquarters

Based in Dallas-Fort Worth

Our office is in Arlington, Texas. We work in Texas and across the United States, and take on international projects case by case.

About the firm


Tell us about your project

Send the asset type, location, size, stage and timing. We will reply to set up a first call.

Institutional lenders: see how we work with you.