Solar, wind, storage and grid projects borrow against revenue that depends on when, and at what cost, they connect to the grid.

Market

What is driving projects

Figures as of November 2026.

  • Under the 2025 federal budget law, wind and solar facilities qualify for the clean electricity tax credits only if they began construction by July 4, 2026 or are placed in service by the end of 2027, and components from certain foreign entities are restricted. Treasury guidance issued in 2025 tightened what counts as beginning construction. Storage keeps a longer schedule.

    (Sources: Public Law 119-21; Internal Revenue Service guidance.)

  • SB 6 requires notice to ERCOT, an ERCOT study and Commission approval before a new large load shares a net metering arrangement with a power plant that was registered as a stand-alone generator as of September 1, 2025.

    (Source: Tex. Util. Code Sec. 39.169, added by SB 6.)

  • Texas's JETI program, which lowers school property taxes for qualifying projects, does not cover non-dispatchable generation (power that cannot be turned up on demand, such as wind and solar) or energy storage.

    (Source: Tex. Gov't Code Ch. 403, Subch. T.)

Capital

Typical capital sources

  • Sponsor equity
  • Investors who fund the project in exchange for its federal tax credits, or buyers of those credits, where the project qualifies
  • Construction and term debt sized to revenue under a long-term power sale contract, or to revenue sold at market prices
  • Equipment financing
  • Where a project raises outside equity, the sponsor's securities counsel and, where required, a registered broker-dealer handle it.

Capital

Revenue structures compared

Illustrative.

StructureWho takes price riskHow lenders size debt
Long-term power sale contractThe buyer, for the contract termOn contracted revenue
Hedge or fixed-volume swapShared, within the hedge termsOn hedged revenue, with volume risk tested
Sales at market pricesThe projectConservatively, on a downside price case

Underwriting

What lenders underwrite

  • Evidence of beginning of construction and the expected in-service date
  • Interconnection agreement and the cost of grid upgrades
  • The revenue contract, or the market price case and its downside
  • Supply chain records for the foreign-entity rules

Underwriting

What we plan for

  • Interconnection studies and upgrade costs
  • Equipment lead times, tariffs and import rules
  • Records that show when construction began

How TJDM helps

How TJDM helps

Headquarters

Based in Dallas-Fort Worth

Our office is in Arlington, Texas. We work in Texas and across the United States, and take on international projects case by case.

About the firm


Tell us about your project

Send the asset type, location, size, stage and timing. We will reply to set up a first call.

Institutional lenders: see how we work with you.